Every Hole in a Glass Panel Is Drilled Before It Is Tempered
Every hole in a glass panel for a railing is drilled before the glass is tempered, which is why one question has such a short window. Somebody asks whether a fixing can be moved over by an inch, and the honest answer is that it can, right up until the panel goes into the furnace, and never again after that.
Why can tempered glass not be drilled on site?
Tempering puts the surface of the glass into compression and the core into tension, and that locked-in stress is what makes the panel strong. Break the surface anywhere, with a drill bit, a score line or a hard knock on an exposed edge, and the stored energy releases through the whole sheet at once. The panel does not chip or crack. It disintegrates. So every hole, notch and rounded corner has to be machined into the raw glass before it is heat treated.
The order a glass panel is made in
The hardware is chosen
Standoffs, clamps, spigots or a base shoe. Each one dictates a different hole pattern, a different edge distance and sometimes a different glass thickness, so this decision has to come first rather than last.
The site is templated
Not from the drawing but from the built structure, with posts standing and the finished floor level known. Every panel is measured in its own position.
The raw glass is cut and machined
The panel is cut to size while it is still ordinary annealed glass. Holes are drilled, notches are cut, corners are radiused and every edge is ground and polished. All of it happens now.
The panel is toughened
Into the furnace, then a rapid controlled quench. The panel comes out tempered and can no longer be cut, drilled or reshaped.
The panel is delivered and set
It either fits or it does not. There is no adjustment left anywhere in the process.

The hinges carrying that panel are not fixed through the frame; they clamp through cutouts in the glass itself. Those cutouts were machined while the sheet was still soft enough to work, and their position was fixed before anyone knew whether the wall behind would end up exactly where the drawing said.
Where the risk actually sits
The panel dimension is the part everyone worries about, but it is not the hardest part. A careful templater takes the opening three ways and allows for the tolerances. The holes are the harder problem, because a hole has to line up with a piece of hardware that is fixed to a wall or a floor that has its own tolerance, and the two have to agree within a couple of millimetres.
A panel that is two millimetres narrow still fits. A hole that is two millimetres out does not.

Each of those standoffs passes through the glass. The spacing between them, their distance from the edges and the diameter of every hole were all settled before the panel existed in its final form.
The rules that govern where a hole can go
A hole too close to an edge concentrates stress exactly where the panel is most vulnerable. Glass processors publish minimum distances and they do not bend.
Corners are the weakest region of any toughened panel. A fixing near one is either moved or the panel is redesigned.
Two holes close together leave a narrow bridge of glass carrying the load between them. There is a minimum for that too.
A hole cannot be smaller than the thickness of the glass. Hardware chosen without checking this is hardware that has to be changed.
The system that needs no holes at all

Where the glass is captured rather than bolted, held in a channel, a base shoe or a wood frame on more than one edge, there are no holes to get wrong and a useful amount of tolerance in the fit. It is a genuinely different design language, less floating and more framed, and it is more forgiving of a building that has moved. It is worth considering on a renovation where the surrounding structure is not new and not perfectly true.
It is also why a damaged panel is such an unwelcome event on a bolted system: there is nothing to adjust, and the replacement has to reproduce the original exactly. We walked through what that actually involves in what replacing a broken glass panel really takes.
Questions about glass panel holes
Can a tempered glass panel be drilled after it arrives?
No. Drilling a tempered glass panel destroys it, because breaking the surface releases the stress locked into the whole sheet at once. Every hole, notch and rounded corner has to exist in the raw glass before the panel goes into the furnace, which is why the hardware and the hole positions are settled before the glass is ordered.
What happens if a hole is in the wrong place?
The panel is scrap and a replacement is ordered. There is no repair, no plug and no re-drill once the glass is tempered. This is why the hardware is confirmed before the glass is measured, not after, and why the posts and the finished floor level need to be in place when the opening is templated.
Is there a way to avoid holes in a glass panel altogether?
Yes. A base shoe or a capture channel grips the bottom edge of the panel and needs no holes at all, and a wood or metal frame can capture the glass on more than one edge, as in the last photo. Those systems trade the floating look for more tolerance in the fit, which helps where the surrounding structure is not perfectly true.
This is the same reason the glass is measured last
Everything above is really one constraint expressed four ways: the glass panel is finalised before it is strengthened, so every dimension it will ever have is fixed before it arrives. That is why glass is not templated from a drawing, why the posts have to be standing first, and why the glass is the last thing measured on a glass railing. The sequencing logic is set out in why glass is measured last, and the rules for guards themselves sit in the province’s published building codes and standards.
Choosing hardware before the glass is ordered
Send us plans or photos of the opening for a quote, and note the look you are after and the hardware you have in mind.