How Early Do You Have to Order a Staircase?

How Early Do You Have to Order a Staircase?

When to order a staircase has an honest answer: earlier than feels necessary, and the reason has nothing to do with how busy any particular shop is. Several stages of a stair project cannot overlap, no matter how much anyone would like them to.

When should a staircase be ordered?

The conversation is best started at design stage, and the stair is measured once the structure is framed and the subfloor is down. What sets stairs apart is that the key stages run in series rather than in parallel: the stair is measured to the real framing, glass panels are made to fit the stair and posts they sit between, and the finishing that follows belongs to your own finisher. Add those together and the path from the first conversation to a finished staircase is longer than the shop time alone suggests.

Why you order a staircase early: the sequence

Design conversation

Layout, materials, finish and grade. This can happen very early, and getting it done early is what makes everything after it possible.

Framing and subfloor complete

The stair is measured to the real building. The opening has to exist, the floor to floor height has to be real, and the subfloor has to be down because it is part of that height.

Site measure

Actual dimensions of the actual building. This is the point where the staircase stops being a drawing.

Fabrication

The part everybody thinks of as the lead time. Ironwood builds straight and curved stairs in its own shop; spiral stairs are built on site.

Installation

The stair is installed on site, and Ironwood covers the treads and landings while the rest of the house is finished around them.

The railing

The railing goes in before the paint and floors are finished, and it is wrapped while the other trades work.

Finishing

Ironwood does not stain or paint, so the finish is applied by your own finisher. The wrap comes off the railing after the paint and floors are done.

Glass, where there is glass

Glass panels are made to fit the stair and the posts they sit between, and tempered glass cannot be cut or drilled once it is made.

Read that list looking for the places where two stages could run at the same time, and there are very few. Glass in particular depends on everything before it, and the reason is set out in why glass is measured last.

Straight staircase with light wood treads, glass along the open side and a black wall handrail

By the time a staircase looks like this, with light wood treads, glass along the open side and a black handrail on the wall, the work has passed through every stage on that list in order.

Where the schedule actually slips

Waiting on a decision

A delay that is easy to avoid. A finish not chosen or a grade not confirmed holds up everything that follows.

Framing running late

Everything after the measure moves by the same amount. The stair cannot start early to make up time it never had.

A change after the measure

Changing a tread material or a post position after the site measure means measuring again, and sometimes making again. Late changes are the hardest kind to absorb.

Glass damage

A broken glass panel cannot be repaired. It has to be made again, which puts that part of the job back at the start of its chain.

The making is only one part of the timeline. The building being ready, and the decisions being made, matter just as much.

Black centre stringer stair with light wood treads and glass guards, a reason to order a staircase early

A stair like this one brings several parts together in one opening: a black centre stringer, light wood treads, and glass with light wood rails. Each has its own place in the sequence, which is one more reason to order a staircase early.

A useful way to think about the dates

Work backwards from the date the house needs to be usable, not forwards from today. The paint and floors are finished after the stair and railing go in, the stair follows the site measure, and the site measure follows the framing. Then find the date the framing has to be complete, and check it against the framing schedule that actually exists rather than the one on the original programme. The province publishes its building codes and standards online, a useful reference while the stair is still on paper.

Where those two dates disagree, that gap is the real answer to how early you need to order a staircase, and knowing it in February is worth a great deal more than discovering it in May.

Dark stained wood posts and handrails with clear glass panels along a stair and landing

What we need before the clock can start

  • The floor to floor height, even approximately, at design stage.
  • Photographs or a plan of the opening.
  • How your finisher will finish the stair: paint, clear finish or both.
  • Whether the railing infill is glass, metal or timber.
  • Your framing completion date, and how confident you are in it.

Information keeps the schedule moving

A decision or a dimension that arrives late holds a stair up as surely as a slow shop would. That is good news, because it means much of the schedule is within your control. What Ironwood needs in order to start is short, specific and mostly things you already know, and it is listed in what we need from you before we can quote.

Questions about when to order a staircase

When should I order a staircase?

Start the conversation at design stage, while layout, materials, finish and grade can still be settled without pressure. The stair itself is measured once the structure is framed and the subfloor is down, so the earlier the decisions are made, the sooner the site measure can follow the framing and the rest of the sequence can begin.

Who finishes the stair, and when?

Ironwood does not stain or paint; the finish is applied by your own finisher. The railing goes in before the paint and floors are finished and is wrapped while other trades work. The wrap comes off after the paint and floors are done, and it should be peeled by hand rather than cut.

What does Ironwood need for a quote?

Photos or a plan of the opening, the floor to floor height if you have it, whether the railing infill will be glass, metal or wood, and your framing completion date. Ironwood works in Calgary and area; call (403) 552-1007 or send the details through the contact page.

Working out when you actually need to start

Send Ironwood photos or plans of the stair, with a note on when the house needs to be finished and where the framing is now.

Start Your Estimate

×
Press Enter to search. E.g., 'glass railings', 'mono stringer', 'calgary'